Project Description:
Sarasota County Utilities Department provides water and wastewater services to 51,000 retail water and 35,000 retail wastewater customers. The Carlton Water Treatment Plant is the world’s largest Electrostatic Dialysis Removal (EDR) plant rated at twelve MGD with an 80% recovery rate.

Transdyn designed, built and installed a complete turnkey countywide SCADA system for the county, including a countywide radio system. A single DYNAC® server manages the county’s distribution system located at the distribution operation facility. Each facility is configured for backup operations in the event of a failure.